Company News · 2026-10-09

Hot Rolling Line Completes Annual Maintenance, Delivery Times Back to Normal

Regular sizes are well stocked following the line restart; reference lead time for regular sizes is 20–30 days, subject to order confirmation and production scheduling.

热轧产线完成年度检修,交期已恢复正常
Company News · 2026-10-09

From 28 September to 6 October, the hot rolling line was shut down for scheduled maintenance, during which the reheating furnace refractories were replaced, the descaling system was upgraded, and the rolling mill housing precision was recalibrated.

On 7 October the entire line passed trial runs on the first attempt, and the surface quality and thickness tolerances of the first hot-rolled coil were within design limits. Stock was built up in advance during the shutdown, so customer orders were not affected.

  • Hot-rolled coil: reference lead time 25 days
  • Medium plate: reference lead time 28 days
  • Cold-rolled substrate: reference lead time 20 days

The above are reference values for regular sizesreference values; actual lead times are subject to order confirmation and current production scheduling, and may be extended by public holidays and port congestion. To secure November capacity, we recommend submitting purchase intentions 30 days in advance.

Need a quote or sample?Provide material, thickness, width and quantity, and we will reply within 24 hours.
Contact Us

Related products and next step

One email a month: grade selection and market notes

The articles like this one, collected into a single email, with nickel price and lead-time movement. No blasts, unsubscribe anytime.

Added to quote list